Construction update at the Hub site
Construction activities of the first phase of The Innovation Hub are progressing well.
The site consists of 31 ha of developable land with a total gross floor area of 121 000 m2. The envisaged completion of the first phase, comprising an Innovation Centre and multi-tenant Enterprise Centre, is towards the end of 2004.
Construction activities since the sod-turning event on 13 October this year, include:
- The bulk earthworks for the Innovation Centre have been completed
- The bulk earthworks for the internal roads are in progress
- The main contracts for the Innovation Centre and bulk electrical supply will be awarded before the year-end break this year
- The main contract for the bridges, including a new N1 bridge and an upgrade of N4 bridge, will also be awarded before the end of this year
- The fencing around the site is nearing completion
- The temporary access road from Kings Highway is completed.
For further information about tenders and the development of the site, click here.